Monday 2 November 2009

Progress this weekend was fairly rapid, thanks in no small part to the army of volunteers who helped us at various times across the weekend. We have installed all of the Finnjoist rafters over the main roof, and the cantilevered tapered firrings, almost all of the plywood deck and almost all of the vapour barrier. Here's an external picture: And internally:

I like the fact that in this picture you can just read 'install this way up' written upside down on several rafters :)

2 comments:

  1. Maybe it's too soon to say but do you have a specific date (or range) when you will be actually living in the house? Will I be able to join you for a beer when I'm back in March? mmm beer

    ReplyDelete
  2. any reason the one firing is shorter then the rest?

    ReplyDelete